Granbury ISD - Middle School - Acton Athletic Facilities

  • Year Built
    2001
  • Square Footage
    2,450
  • Replacement Cost
    $3,294,168
  • Condition Budget
    $1,682,876
  • Facility Condition Index
    71%
Condition Assessment
System Rating Score
  • Good

  • Fair

    (or will require attention in near future 3-10 years)

  • Poor

    (or will require attention now 0-2 years)

Exterior

Fair
Exterior Structure: Fill open holes in wall surface, replace any cracking or missing caulking around penetrations. Check fasteners and flashings for tightness and seal on metal walls, repair or replace as needed.
Good
Foundation: No issues observed or reported.
Poor
Site: Repair uneven pedestrian paved surfaces to reduce potential tripping hazards.
Fair
Doors: Refresh exterior hollow metal door finished surfaces as needed.
Good
Exterior/Interior Windows: No issues observed or reported.
Good
Roof: Check fasteners and caulking on metal (R panel & Standing Seam) roof system for tightness and seal, repair or replace as needed. Roof systems should be inspected at least semi-annually and after every significant weather event.

Interior

Fair
Interior Structure: Refresh high touched interior masonry wall finished surfaces. Repair and refinish wallboard ceiling surfaces as needed.
Good
Plumbing: No issues observed or reported.
Good
ADA: No issues observed or reported.
Good
Furnishing, Fixtures, Equipment: Repair or replace aged or damaged cabinets and countertops as needed.
Fair
Electrical: Update lighting fixtures to LED.
Fair
Safety/Security: Review and consider Safety & Security Recommendations on the Facility Details page.
Good
Flooring: No issues observed or reported.
Good
HVAC: No HVAC systems at this facility.

Priority Projects

  • Check fasteners and caulking on metal (R panel) roof system for tightness and seal, repair or replace as needed.
  • Check fasteners and caulking on metal (standing seam) roof system for tightness and seal, repair or replace as needed.
  • Check fasteners and flashings for tightness and seal on metal walls, repair or replace as needed.
  • Fill open holes in wall surface, replace any cracking or missing caulking around penetrations.
  • Repair and refinish wallboard ceiling surfaces as needed.
  • Update lighting fixtures to LED.
  • Repair uneven pedestrian paved surfaces to reduce potential tripping hazards.
  • Repair and resurface track structural topcoat.

Additional Projects, if Funds Become Available

  • Refresh exterior hollow metal door finished surfaces as needed.
  • Refresh high touched interior masonry wall finished surfaces.
  • Repair or replace aged or damaged cabinets and countertops as needed.
  • Update football field lighting to LED.

Actions to Improve the Educational Environment