Granbury ISD - High School - Fieldhouse, Pirate Pavilion, Track
- Year Built1999,2003
- Square Footage46,365
- Replacement Cost$36,103,582
- Condition Budget$2,765,005
- Facility Condition Index9%
Condition Assessment
System Rating ScoreGood
Fair
(or will require attention in near future 3-10 years)
Poor
(or will require attention now 0-2 years)
Exterior
Fair
Exterior Structure: Repair or replace damaged metal wall panels as needed. Re-seal the building envelope by regrouting or repointing the masonry work, filling holes, and replacing cracking or missing caulking around penetrations.
Poor
Foundation: There are indicators of foundation movement by cracking in exterior masonry blocks, recommend engineering study to determine cause and proper mitigation.
Fair
Parking/Traffic: Remove damaged asphalt surface, repair base, replace asphalt surfacing, seal area, and restripe as needed.
Fair
Site: Repair field irrigation system. Review and consider Safety & Security Recommendations on the Facility Details page.
Fair
Doors: Repair and refresh interior wood door finished surfaces as needed. Refresh interior finished hollow metal and rollup door surface as needed. Refresh exterior hollow metal door finished surfaces as needed.
Good
Exterior/Interior Windows: No issues observed or reported.
Poor
Roof: Modified Bitumen roof is past useful life expectancy and should be planned for replacement. Until replacement can occur, the roof should be inspected at least semi-annually and after every significant weather event. Metal standing seam - Continue maintenance as per manufacturer's recommendations and inspect roof at least twice annually and after every significant weather event.
Interior
Poor
Interior Structure: Cracking observed in masonry and framed interior walls, repair walls, fill gaps, and refinish surface, observe for change, if movement persists engineering study is recommended to determine cause and mitigation. Clean and prepare interior metal panel surface removing oxidation, re-seal surface and paint. Refresh high touched interior masonry and wallboard wall finished surfaces. Replace stained or damaged 2x2 lay-in ceiling tiles as needed. Repair and refinish wallboard ceiling surfaces as needed.
Good
Plumbing: No issues observed or reported.
Good
ADA: No issues observed or reported.
Fair
Furnishing, Fixtures, Equipment: Repair or replace fixed furnishings (cabinets, counter tops, lockers) as needed. Repair or replace damaged moveable furnishings as needed. Update restroom accessories, stalls and showers as needed.
Fair
Electrical: Update lighting fixtures to LED. Review and consider Safety & Security Recommendations on the Facility Details page.
Fair
Safety/Security: Review and consider Safety & Security Recommendations on the Facility Details page.
Fair
Flooring: Deep clean, reseal surface cracking, and refresh finished floor surface on liquid applied and polished concrete flooring. Replace carpet that is damaged, stained, or past useful life expectancy.
Poor
HVAC: HVAC system components at or past their useful life expectancy should be replaced. Test and balance new HVAC units when installed.
Priority Projects
- Modified Bitumen roof is past useful life expectancy and should be planned for replacement. Until replacement can occur, the roof should be inspected at least semi-annually and after every significant weather event.
- There are indicators of foundation movement by cracking in exterior masonry blocks, recommend engineering study to determine cause and proper mitigation.
- Repair or replace damaged metal wall panels as needed.
- Cracking observed in framed partitions of the interior walls, repair walls, fill gaps and refinish surface; observe for movement.
- Cracking observed in masonry work, observe for change, if movement persists engineering study is recommended to determine cause and mitigation.
- Refresh high touched interior masonry wall finished surfaces.
- Replace carpet that is damaged, stained, or past useful life expectancy.
- Repair and refinish wallboard ceiling surfaces as needed.
- Replace stained or damaged 2x2 lay-in ceiling tiles as needed.
- Update lighting fixtures to LED.
- Remove damaged asphalt surface, repair base, replace asphalt surfacing, seal area, and restripe as needed.
- Repair field irrigation system.
- Track structure and base is deteriorating and should be replaced.
- Repair or replace track jump pits as needed.
- Apply new structural topcoat to running track.
- Test and balance new HVAC units when installed.
Additional Projects, if Funds Become Available
- Refresh exterior hollow metal door finished surfaces as needed.
- Refresh exterior rollup metal door finished surfaces as needed.
- Repair and refresh interior wood door finished surfaces as needed.
- Refresh finished hollow metal door surface as needed.
- Refresh wallboard paint wall surface and repair as needed.
- Clean and prepare surface removing oxidation, re-seal surface and paint.
- Deep clean, reseal surface cracking, and refresh finished floor surface on polished concrete flooring.
- Deep clean, reseal surface cracking, and refresh finished floor surface on liquid applied flooring.
- Update restroom accessories, stalls and showers as needed.
- Repair or replace fixed furnishings (cabinets, counter tops, lockers) as needed.
- Repair or replace damaged moveable furnishings as needed.
Utilization
0% Capacity: Low Utilized
Capacity
Pupil Count
Student Enrollment
Functional Capacity
Facility Condition Index
FCI: 9%
Educational Adequacy Assessment
System Rating ScoreAdequate Spaces
Needs Improvement
Not Adequate
Good
Occupant Flow: Pedestrian traffic flow within the building is good.
Fair
Security: Review Safety & Security recommendations on the Facility Details page.
Poor
Site Playgrounds/Extra Curricular: Track is in poor condition and needs to be replaced. Fieldhouse and Pirate Pavillion support the basic athletic program needs.
Actions to Improve the Educational Environment
These athletic facilities support the district’s goals for student-athletes. Completing upgrades and improvements will help enhance the learning environment and better support those goals.