Granbury ISD - Operations - Transportation
- Year Built1977,2000,2001
- Square Footage8,072
- Replacement Cost$5,352,156
- Condition Budget$735,193
- Facility Condition Index17%
Condition Assessment
System Rating ScoreGood
Fair
(or will require attention in near future 3-10 years)
Poor
(or will require attention now 0-2 years)
Exterior
Fair
Exterior Structure: Re-seal the building envelope by checking fasteners and flashings for tightness and seal on the metal walls, repair or replace as needed. Repair or replace wooden structural support members and siding as needed to return wood siding wall to original condition and stiffness.
Fair
Foundation: Repair or replace wooden structural support members and decking as needed to return flooring to original elevation and stiffness.
Fair
Parking/Traffic: Slurry coat asphalt roadway and parking surfaces and restripe.
Fair
Site: Clean area around the bus barn.
Fair
Doors: Replace interior doors, hardware, and finish surfaces as needed. Refresh exterior hollow metal door finished surfaces as needed.
Fair
Exterior/Interior Windows: Update single pane window systems with energy efficient window systems.
Poor
Roof: The Asphalt shingle and Metal R Panel roof systems at the Transportation facility are past life expectancy and should be planned for replacement. Until replacement can occur, the roofs should be inspected at least semi-annually and after every significant weather event.
Interior
Poor
Interior Structure: Repair or replace wooden structural support members and decking as needed to return flooring to original elevation and stiffness. Refresh high touched interior wallboard paint wall finished surfaces. Replace damaged and aged 4X2 ceiling tiles with 2X2 grid and tiles.
Fair
Plumbing: Repair, replace, or re-install damaged and missing or non-ADA compliant plumbing fixtures as needed.
Fair
ADA: Update plumbing fixtures for ADA compliance.
Fair
Furnishing, Fixtures, Equipment: Repair or replace aged or damaged cabinets and countertops as needed.
Fair
Electrical: Mechanical systems 30 years or older should be inspected and repaired or replaced as inspection dictates; Funding for system inspections. Update lighting fixtures to LED. Review and consider Safety & Security Recommendations on the Facility Details page.
Fair
Safety/Security: Review and consider Safety & Security Recommendations on the Facility Details page.
Fair
Flooring: Replace damaged vinyl floor tile.
Poor
HVAC: The Transportation facility currently operates with three HVAC units. Of these, one unit has already exceeded its expected service life, while the remaining two are projected to reach the end of their life expectancy by 2029. To ensure continued reliability and maintain optimal energy efficiency, it would be prudent for the district to begin planning for the replacement of all three units.
Priority Projects
- Asphalt shingle roof is past useful life expectancy and should be planned for replacement. Until replacement can occur, the roof should be inspected at least semi-annually and after every significant weather event.
- Metal R Panel roof is past useful life expectancy and should be planned for replacement. Until replacement can occur, the roof should be inspected at least semi-annually and after every significant weather event.
- Repair or replace wooden structural support members and decking as needed to return flooring to original elevation and stiffness.
- Repair or replace wooden structural support members and siding as needed to return wall to original condition and stiffness.
- Re-seal the building envelope by checking fasteners and flashings for tightness and seal on the walls, repair or replace as needed.
- Replace interior doors, hardware, and finish surfaces as needed.
- Replace damaged vinyl floor tile.
- Replace damaged and aged 4X2 ceiling tiles with 2X2 grid and tiles.
- Repair, replace, or re-install damaged and missing or non-ADA compliant plumbing fixtures as needed.
- Mechanical systems 30 years or older should be inspected and repaired or replaced as inspection dictates; Funding for system inspections.
Additional Projects, if Funds Become Available
- Update single pane window systems with energy efficient window systems.
- Refresh exterior hollow metal door finished surfaces as needed.
- Refresh high touched interior wallboard paint wall finished surfaces.
- Update lighting fixtures to LED.
- Repair or replace aged or damaged cabinets and countertops as needed.
- Slurry coat asphalt surfaces and restripe roadways.
- Slurry coat asphalt surfaces and restripe parking spaces.
Actions to Improve the Educational Environment
This facility is a support facility for district.