Lyford CISD - Main Campus - Auditorium

  • Year Built
    1958
  • Square Footage
    8,344
  • Replacement Cost
    $3,132,004
  • Condition Budget
    $3,621,663
  • Facility Condition Index
    167%
Condition Assessment
System Rating Score
  • Good

  • Fair

    (or will require attention in near future 3-10 years)

  • Poor

    (or will require attention now 0-2 years)

Exterior

Fair
Exterior Structure: Bricks on the Auditorium are in fair condition but there are areas with significant cracks that need to be repaired. A structural evaluation should be completed on this structure.
Fair
Foundation: Repair minor cracking at corners along perimeter.
Poor
Parking/Traffic: Drives and parking information included in the ES report. Overall fair to poor condition.
Fair
Site: Sidewalk information included in the ES report. Additional pole and perimeter lighting needed at all buildings and points of entry.
Fair
Doors: Replace all exterior wooden doors and frames. Replace damaged interior and exterior doors and frames. Repaint those in fair to good condition. Not all hardware is ADA compliant.
Fair
Exterior/Interior Windows: Refinish exterior window units.
Poor
Roof: Roofs on the Administration is in poor condition. Leaks are visible inside the main auditorium and have impacted ceiling tiles within. Past termite damage is visible on exterior fasci and the roof system should be evaluated. Due to the age and the signs of deterioration, it should all be considered for replacement.

Interior

Fair
Interior Structure: Termite damage to flooring, walls and some of the roof structural components. Replace any damaged material to these systems and have evaluated for structural integrity. Replace damaged and worn flooring, and repaint all wall surfaces. Replace damaged and sagging ceiling tiles with 2x2' grid system.
Plumbing: N/A
Poor
ADA: Accessibility is poor overall. Non-compliant entryways, ramps, pathways between and within the structure, restrooms and door hardware should all be addressed.
Fair
Furnishing, Fixtures, Equipment: Auditorium seating in is fair condition but lacks ADA seating. All non-compliant and damaged restroom stalls, accessories and fixtures should be replaced. Furniture in stage areas is in poor condition and should be replaced.
Fair
Electrical: Consider replacing electrical infrastructure that is 30 years old or older. Overhead power lines should be placed under ground.
Fair
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Fair
Flooring: Replace all damaged flooring.
Poor
HVAC: All 4 of the HVAC units (100% of the cooling capacity) are past their expected life span and will need to be replaced. HVAC control upgrades and testing & balancing should be performed during HVAC replacement. Several fountains and plumbing fixtures are damaged or do not meet ADA standards and need to be replaced. Consider replacing electrical or plumbing infrastructure that is 30 years old or older.

Priority Projects

  • Repair all damage to exterior surfaces; structural evaluation of buildings should be completed.
  • Replace all non-ADA complaint hardware.
  • Replace roofing system and evaluate wooden substructure for damage.
  • Replace all HVAC systems and supporting electrical components nearing the end of their useful life.

Additional Projects, if Funds Become Available

  • Bury overhead power lines.
  • Structural evaluation.
  • Replace all damaged floor and wall finishes.
  • Add additional pole and perimeter lighting.
  • Consider replacing all electrical and plumbing infrastructure that is 30 years or older.