Anderson-Shiro CISD - AS High School - Ag Farm

  • Year Built
    2010
  • Square Footage
    15,100
  • Replacement Cost
    $6,925,509
  • Condition Budget
    $186,267
  • Facility Condition Index
    3%
Condition Assessment
System Rating Score
  • Good

  • Fair

    (or will require attention in near future 3-10 years)

  • Poor

    (or will require attention now 0-2 years)

Exterior

Fair
Exterior Structure: Clean exterior walls and treat with algaecide. Paint exterior metal surfaces as needed. Seal around AC unit.
Good
Foundation: No issues observed or reported.
Fair
Parking/Traffic: Included in Main building.
Poor
Site: Included in Main building.
Good
Doors: No issues observed or reported.
Exterior/Interior Windows: No windows present.
Good
Roof: Roof is in good condition. Maintenance of fasteners, joints and structure and overall cleaning needed to ensure expected life.

Interior

Poor
Interior Structure: Replace paving sealants. Replace interior wall sealants. Paint walls as needed. Replace damaged ceiling in concessions area. Test and remediate for mold. Paint interior structure.
Plumbing: N/A
Good
ADA: No issues observed or reported.
Good
Furnishing, Fixtures, Equipment: No issues observed or reported.
Fair
Electrical: Replace rusting light fixtures and corroded fans. Provide building mounted security lighting at all entrances.
Fair
Safety/Security: See Safety & Security recommendations on Facility Details page.
Good
Flooring: No issues observed or reported.
Good
HVAC: No issues observed or reported.

Priority Projects

  • Provide Safety & Security Improvements.
  • Test and remediate for mold.
  • Repair roof leak that caused major damage in concession area.
  • Replace damaged ceiling in concessions area.

Additional Projects, if Funds Become Available

  • Provide accessible signage.
  • Paint exposed structure in pen/arena area.
  • Clean exterior walls and treat with algaecide.
  • Paint exterior metal surfaces as needed.
  • Seal around AC unit.
  • Replace paving, interior wall sealants.
  • Paint walls as needed.
  • Paint interior structure.
  • Replace rusting light fixtures and corroded fans.
Educational Adequacy Assessment
System Rating Score
  • Adequate Spaces

  • Needs Improvement

  • Not Adequate

Core Classrooms:
Visual and Performing Arts:
Cafeteria:
Good
Occupant Flow: Spaces dedicated to circulation are adequate for the needs of the facility.
Fair
Security: See Safety & Security recommendations on the Facility Details page.
Site Playgrounds/Extra Curricular:
Special Education:
Physical Education:
Library:
Administration:

Actions to Improve the Educational Environment

The educational environment is good. Improvements include cleaning, replacement of rusted equipment, safety and security improvements and future additions that would include instructional spaces.