Anderson-Shiro CISD - Old School Site - Gymnasium (Main)
- Year Built1988
- Square Footage8,700
- Replacement Cost$4,541,270
- Condition Budget$3,376,086
- Facility Condition Index86%
Condition Assessment
System Rating ScoreGood
Fair
(or will require attention in near future 3-10 years)
Poor
(or will require attention now 0-2 years)
Exterior
Fair
Exterior Structure: Replace damaged siding after foundation corrections.
Poor
Foundation: Secure a structural evaluation of foundation to determine future steps. Correct issues identified by engineering evaluation. Provide adequate airways and crawlspace access.
Fair
Parking/Traffic: Replace roadway and parking paving and restripe.
Fair
Site: Replace sidewalks. Trim trees and shrubbery back from building and roof line. Regrade to remove soil from contact with exterior walls and to provide positive drainage away from the building.
Poor
Doors: Replace wooden exterior doors, frames and hardware. Replace interior doors, frames and obsolete door hardware.
Poor
Exterior/Interior Windows: Replace original window units.
Poor
Roof: Identify source of interior water damage and repair. Maintain fasteners and sealants. If facility is to be kept in district's inventory, begin planning for the installation of gutters and downspouts.
Interior
Fair
Interior Structure: Repair and paint plaster walls. Paint interior walls. Repair damaged wood planking. Sample for ACM, lead and abate as needed. Replace damaged wood plank ceilings. Remove peeling paint accordingly. Paint painted ceilings. Replace 1x1 glue up tiles with 2x2 system.
Plumbing: N/A
Poor
ADA: Building is not accessible. Parking, approaches, entrances, seating and restrooms lack accessibility.
Fair
Furnishing, Fixtures, Equipment: Provide accessible seating.
Poor
Electrical: Replace mechanical infrastructure older than 30 years. Replace OH electrical service.
Poor
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Fair
Flooring: Replace vinyl floor coverings. Repaint concrete floors.
Poor
HVAC: Replace damaged, old and obsolete fixtures to provide accessible restrooms. Replace mechanical infrastructure older than 30 years. Replace ductwork and HVAC grilles. Replace ventilation fans and louvers. Provide centralized HVAC system.
Priority Projects
- Sample for ACM, lead and abate as needed.
- Secure a structural evaluation of foundation to determine measures needed; correct issues identified by engineering evaluation and provide adequate airways and crawlspace access.
- Repair leaks evidenced by interior water damage.
- Replace sidewalks.
- Regrade to remove soil from contact with exterior walls and to provide positive drainage away from the building.
- Trim trees and shrubbery back from building and roof line.
- Provide Safety & Security improvements.
- Provide accessible routes at all entrances.
- Install proper pipe supports under building.
- Provide accessible seating in gym.
- Renovate restrooms to provide accessibility.
- Provide accessible signage.
- Conduct IAQ testing, remediate as needed, identify source of moisture and repair.
Additional Projects, if Funds Become Available
- Provide Voice / Data System.
- Provide Closed Circuit Surveillance.
- Provide Access Control System.
- Provide Intrusion Alarm System
- Provide Fire Alarm / Detection.
- Provide Lighting Control System.
- Expand parking to accommodate seating capacity of 260 with 30 additional spaces to bring total to 65.
- Provide gutters and downspouts.
- Provide HVAC system for building.
- Provide accessible routes at all entrances.
- Install proper pipe supports under building.
- Provide accessible seating in gym.
- Renovate restrooms to provide accessibility.
- Provide accessible signage.
- Provide additional site lighting.
- Remove fencing and structures from old softball field an old bus yard.
- Conduct IAQ testing, remediate as needed, identify source of moisture and repair.
- Renovate corridors to allow adequate space for circulation.
- Repair damaged wood planking and plaster walls.
- Paint interior walls.
- Replace damaged wood plank ceilings and paint painted ceilings.
- Replace 1x1 glue up tiles with 2x2 system.
- Replace damaged siding after foundation corrections.
- Replace damaged, old and obsolete fixtures to provide accessible restrooms.
- Replace mechanical infrastructure older than 30 years.
- Replace ductwork and HVAC grilles, ventilation fans and louvers.
- Provide centralized HVAC system.
- Maintain fasteners, sealants; repair soffit and fascia.
- Replace roadway and parking paving and restripe.
- Provide accessible seating.
- Replace OH electrical service.
- Replace wooden exterior and interior doors, frames and door hardware.
- Replace original window units.
- Replace vinyl floor coverings.
- Repaint concrete floors.
- Provide Voice / Data System.
- Provide Lighting Control System.
- Expand parking to accommodate seating capacity of 260 with 30 additional spaces to bring total to 65.
- Provide gutters and downspouts.
- Provide HVAC system for building.
- Remove fencing and structures from old softball field an old bus yard.
- Renovate corridors to allow adequate space for circulation.
Educational Adequacy Assessment
System Rating ScoreAdequate Spaces
Needs Improvement
Not Adequate
Core Classrooms:
Visual and Performing Arts:
Cafeteria:
Fair
Occupant Flow: Occupant flow is inhibited by lack of accessibility at entrances and narrow passages and doorways.
Poor
Security: See Safety & Security recommendations on the Facility Details page.
Site Playgrounds/Extra Curricular:
Special Education:
Fair
Physical Education: The facility's remote location, aged and limited facilities inhibit its use as an instructional facility.
Library:
Administration:
Actions to Improve the Educational Environment
The educational environment in the facility is fair. Issues contributing to this is the facility's remote location, aging and missing systems and components, safety and security deficiencies, and lack of accessibility. Extensive work is needed to bring this facility up to modern standards.