Elementary School - Multipurpose and Primary

  • Year Built
    2002
  • Square Footage
    18,000
  • Replacement Cost
    $10,122,863
  • Condition Budget
    $1,607,287
  • Facility Condition Index
    19%
Condition Assessment
System Rating Score
  • Good

  • Fair

    (or will require attention in near future 3-10 years)

  • Poor

    (or will require attention now 0-2 years)

Exterior

Poor
Exterior Structure: Prep and repaint exterior metal panels. Inspect and repair exterior expansion caulking to prevent moisture and pests from getting inside the building. Repair damaged masonry walls.
Fair
Foundation: Possible foundation movement was observed at rear of primary building. Consider contracting with an engineer to determine cause and solutions for movement. Continue monitoring for movement.
Fair
Parking/Traffic: Included with Elementary Office and 400 Wing.
Poor
Site: Address drainage issues at Primary building. Area around building should be graded to direct water away from the building.
Fair
Doors: Refinish interior and exterior doors.
Poor
Exterior/Interior Windows: Replace windows with double paned energy efficient windows. Inspect and repair or replace exterior window caulking.
Good
Roof: Area 1 - Primary building - Overall the metal roof is in good condition. Gutters and downspouts should be inspected and repaired or replaced as needed. The roof should be inspected annually and after every significant weather event to maintain effectiveness. The roof should be inspected annually and after every significant weather event to maintain effectiveness. Area 2 - Multipurpose building - Overall the metal roof is in good condition. The roof seams should be inspected regularly to ensure water tightness. Gutters and downspouts should be inspected and repaired or replaced as needed. The roof should be inspected annually and after every significant weather event to maintain effectiveness.

Interior

Fair
Interior Structure: Repaint high touch interior walls. Repaint multipurpose walls. Replace damaged ceiling tiles as needed. Update primary restrooms and hallways with an updated color scheme.
Plumbing: N/A
Poor
ADA: Accessible signage and updating door hardware is needed to meet ADA compliance.
Fair
Furnishing, Fixtures, Equipment: Repair or replace damaged restroom accessories.
Fair
Electrical: Install lighting control system. Update lighting in multipurpose building to LED fixtures.
Poor
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Fair
Flooring: Clean floor tile and replace damaged flooring as needed. Clean ceramic tile and grout, repair damaged tiles.
Poor
HVAC: Repair damaged water fountain in Multipurpose. Replace HVAC system components beyond useful life expectancy. Replace ductwork as necessary when updating HVAC system components. Replace HVAC controls and instrumentation. Test and balance new HVAC systems.

Priority Projects

  • Inspect and repair exterior expansion caulking.
  • Contract with an engineer to determine cause and solutions for possible foundation movement at Primary Building.
  • Replace HVAC system components beyond useful life expectancy.
  • Replace HVAC controls and instrumentation; Test and balance new HVAC systems.
  • Inspect gutters and downspouts and repair or replace as necessary.
  • Address drainage issues at Primary building; Area around building should be graded to direct water away from the building.
  • Update lighting LED fixtures; Install lighting control system.
  • Refinish interior and exterior doors and update door hardware to meet ADA compliance.
  • See Safety & Security recommendations on the Facility Details page.
  • Inspect and repair or replace exterior window caulking.

Additional Projects, if Funds Become Available

  • Vestibule
  • Drainage
  • Enclosed Walkways
  • Prep and repaint exterior metal panels.
  • Repair damaged masonry walls.
  • Repaint high touch interior walls.
  • Repaint multipurpose walls.
  • Replace damaged ceiling tiles as needed.
  • Update primary restrooms and hallways with an updated tile and color scheme.
  • Repair damaged water fountain in Multipurpose building.
  • Repair or replace damaged restroom accessories.
  • Replace windows with double paned energy efficient windows.
  • Clean floor tile and replace damaged flooring as needed.
  • Clean ceramic tile and grout, repair damaged tiles.
  • Construct enclosed walkways.
Educational Adequacy Assessment
System Rating Score
  • Adequate Spaces

  • Needs Improvement

  • Not Adequate

Good
Core Classrooms: Core classrooms are generally in good condition.
Visual and Performing Arts:
Cafeteria:
Good
Occupant Flow: Occupant flow within the facility appears adequate.
Poor
Security: See Safety & Security recommendations on the Facility Details page.
Site Playgrounds/Extra Curricular:
Special Education:
Good
Physical Education: Physical education space is in good condition. However, it could be improved with repainting the walls and updating the lighting in the multipurpose building.
Library:
Administration:

Actions to Improve the Educational Environment

The educational environment of the facility is in good condition. Updating HVAC system components beyond their useful life expectancy, updating light fixtures to LED, and repainting the interior will improve the educational environment.