Gonzales ISD - North Avenue Intermediate - Cafeteria & 300 Buildings
- Year Built1949
- Square Footage19,936
- Replacement Cost$7,950,876
- Condition Budget$1,264,069
- Facility Condition Index23%
Condition Assessment
System Rating ScoreGood
Fair
(or will require attention in near future 3-10 years)
Poor
(or will require attention now 0-2 years)
Exterior
Fair
Exterior Structure: Exterior structure is generally in good-to-fair condition. Repair and repaint stucco soffits and repair brick cracks on south side of 300 building.
Good
Foundation: No issues observed.
Fair
Parking/Traffic: Parking surfaces are in fair condition; cracking and damage was observed. Repair and reseal of parking areas is needed.
Good
Site: No issues observed.
Fair
Doors: Repaint exterior metal doors.
Fair
Exterior/Interior Windows: Windows are in good-to-fair condition. Oxidized window frames at 300 building need refinishing.
Roof: N/A
Interior
Fair
Interior Structure: Interior structure is generally in good-to-fair condition. Repaint wallboard walls in 300 building and replace ceiling tiles in 300 building.
Plumbing: N/A
Fair
ADA: Generally good ADA access on campus. Improvements needed to exterior ramp at cafeteria and interior room signage in 300 building.
Good
Furnishing, Fixtures, Equipment: FFE is generally in good condition.
Fair
Electrical: Replace electrical and lighting infrastructure older than 30 years.
Poor
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Fair
Flooring: Flooring is generally in good-to-fair condition. Replacement of cracked and damaged VCT is needed in 300 building.
Fair
HVAC: Several aging HVAC units; replace 2 package units. Much of the plumbing infrastructure is greater than 30 years old and should be considered for replacement.
Priority Projects
- Repair exterior masonry cracks on south side of 300 building.
- Replace 2 aging HVAC units.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
Additional Projects, if Funds Become Available
- Repair and repaint stucco soffits.
- Repaint exterior metal doors and refinish oxidized window frames at 300 building.
- Repaint wallboard walls in 300 building and replace ceiling tiles in 300 building.
- Replace cracked and damaged VCT in 300 building.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
- Begin planning for replacement of built-up gravel roof on 300 building within the next 10 years.
Utilization
67% Capacity: Moderately Utilized
Capacity
Pupil Count
Student Enrollment
420
Functional Capacity
627
Facility Condition Index
FCI: 23%
Educational Adequacy Assessment
System Rating ScoreAdequate Spaces
Needs Improvement
Not Adequate
Good
Core Classrooms: Rooms are generally in good condition.
Visual and Performing Arts: Not applicable at this facility.
Good
Cafeteria: Cafeteria is adequately sized to serve campus when at or near full capacity.
Occupant Flow: N/A
Poor
Security: See Safety & Security recommendations on the Facility Details page.
Site Playgrounds/Extra Curricular: Not applicable at this facility.
Good
Special Education: Rooms are generally in good condition and satisfy basic special education program needs.
Physical Education: Not applicable at this facility.
Library: Not applicable at this facility.
Administration: Not applicable at this facility.
Actions to Improve the Educational Environment
The educational environment of the facility is in good condition; however, campus layout with multiple buildings is not conducive to modern learning strategies. Security enhancements to campus should be made. Minor maintenance improvements are needed.