Breckenridge ISD - North Elementary - Gym
- Year Built2008
- Square Footage5,216
- Replacement Cost$2,614,948
- Condition Budget$538,547
- Facility Condition Index24%
Condition Assessment
System Rating ScoreGood
Fair
(or will require attention in near future 3-10 years)
Poor
(or will require attention now 0-2 years)
Exterior
Poor
Exterior Structure: Re-seal the building envelope by checking fasteners and flashings for tightness and seal on the walls, repair or replace as needed.
Remove any material at the wall base, remove oxidation, apply inhibitor, reseal, refresh finish surface or replace panel section if rusted through.
Poor
Foundation: Promote stable soil conditions around foundation by creating positive storm water drainage away from structure and eliminating standing water next to foundation.
Parking/Traffic: N/A
Poor
Site: install ADA compliant landings at exterior doors.
Poor
Doors: Update door hardware and refresh finish surfaces.
Replace weatherstripping and door sweeps on exterior doors as needed.
Exterior/Interior Windows: N/A
Good
Roof: Area 1: As per 2023.09update survey roof was replaced 8/2023. Continue maintenance as per manufacturer's recommendations. Observe roof at least annually and after any major weather event.
Interior
Fair
Interior Structure: Repair wall surface and refresh finished surfaces.
Replace damaged and stained ceiling tiles as needed.
Clean and refresh finished ceiling surfaces.
Plumbing: N/A
Poor
ADA: Recommend ADA compliant landing at all exterior doors.
Facility should have an ADA accessible route connecting compliant parking, compliant building entrances to all campus buildings, public areas within the buildings, and compliant restrooms.
Fair
Furnishing, Fixtures, Equipment: Repair or replace damaged shelving, cabinets, and countertops when needed.
Replace damaged moveable furnishings when needed.
Fair
Electrical: Install LED lighting if building is to occupied by students.
Remove all obstruction restricting access to electrical panels; Label floor if needed.
Update to fiber cabling and devices to support secure Wi-Fi as needed if building is to occupied by students.
Install lighting control system if building is to occupied by students.
Poor
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Fair
Flooring: Deep clean, repair or replace aged and damaged flooring as needed for use.
Fair
HVAC: Replace heating units at or past their useful life expectancy.
Replace window AC unit at or past it's useful life expectancy.
Priority Projects
- See Safety & Security recommendations on the Facility Details page.
- Update door hardware and refresh finish surfaces.
- Replace weatherstripping and door sweeps on exterior doors as needed.
- Remove all obstruction restricting access to electrical panels; Label floor if needed.
- Recommend ADA compliant landing at all exterior doors.
- Check fasteners and flashings on roof system for tightness and seal, repair or replace as needed.
- Creating positive storm water drainage away from structure and eliminate standing water next to foundation.
- Re-seal the building envelope by checking fasteners and flashings for tightness and seal on the walls, repair or replace as needed.
- Remove any material at the wall base, remove oxidation, apply inhibitor, reseal, refresh finish surface or replace panel section if rusted through.
Additional Projects, if Funds Become Available
- Install a secure entry vestibule if facility is to be occupied by students with no connecting corridor.
- Deep clean, repair or replace aged and damaged flooring as needed for use.
- Install LED lighting if building is to occupied by students.
- Update to fiber cabling and devices to support secure Wi-Fi as needed if building is to occupied by students.
- Install lighting control system if building is to occupied by students.
- Repair or replace damaged shelving, cabinets, and countertops when needed.
- Replace damaged moveable furnishings when needed.
- Replace window AC and ceiling heaters as the use requires.
- Repair interior wall surface and refresh finished surfaces.
- Replace damaged and stained ceiling tiles as needed.
- Clean and refresh finished ceiling surfaces.
- See Safety & Security recommendations on the Facility Details page.
Educational Adequacy Assessment
System Rating ScoreAdequate Spaces
Needs Improvement
Not Adequate
Core Classrooms:
Visual and Performing Arts:
Cafeteria:
Occupant Flow:
Poor
Security: See Safety & Security recommendations on the Facility Details page.
Site Playgrounds/Extra Curricular:
Special Education:
Good
Physical Education: Gym is adequately sized for a elementary school campus.
Library:
Administration:
Actions to Improve the Educational Environment
At the time of the site visit the North Elementary School campus was not occupied by students and is predominantly storage. Substantial renovations, updates, and additions would be recommended before campus is occupied by students.