Breckenridge ISD - Breckenridge Main Campus - ALC and DAEP

  • Year Built
    1965
  • Square Footage
    1,463
  • Replacement Cost
    $425,306
  • Condition Budget
    $92,308
  • Facility Condition Index
    25%
Condition Assessment
System Rating Score
  • Good

  • Fair

    (or will require attention in near future 3-10 years)

  • Poor

    (or will require attention now 0-2 years)

Exterior

Poor
Exterior Structure: As per 2023.09 update survey replacement of broken and cracked vinyl siding on walls is scheduled.
Good
Foundation: No issue observed or reported.
Parking/Traffic: N/A
Site: N/A
Poor
Doors: Repair or replace doors and hardware as needed for ADA accessibility and refresh finish surfaces. Replace weatherstripping and door sweeps on exterior doors as needed.
Poor
Exterior/Interior Windows: Repair or replace damaged or missing window seals and re-caulk frame as needed.
Fair
Roof: Area 1: As per 2023.09 update survey roof is in progress. Trim all vegetation overhanging roof. Install gutter, downspouts, and splash blocks. Continue maintenance as per manufacturer's recommendations. Observe roof at least annually and after any major weather event.

Interior

Fair
Interior Structure: Refresh high touched interior wall finished surfaces. Refresh painted ceiling finished surfaces.
Plumbing: N/A
Poor
ADA: Facility is not fully compliant, updates should be done to kitchen counter and sink as well as installing proper ADA signage. Maintain ADA required clearance to ramps, doors, and plumbing fixtures, remove stored items impinging on clearances.
Fair
Furnishing, Fixtures, Equipment: Update restroom accessories and stalls for ADA compliance as needed. Repair or replace aged or damaged cabinets and countertops as needed. Replace damaged moveable furnishings as needed.
Fair
Electrical: Install additional receptacles in classroom. Install LED lighting. As per 2023.09 update survey project underway for data and intercom. Install lighting control system.
Poor
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Fair
Flooring: Deep clean, repair or replace aged and damaged flooring.
Poor
HVAC: Update to ADA compliant plumbing fixtures in kitchen area.

Priority Projects

  • See Safety & Security recommendations on the Facility Details page.
  • Repair or replace damaged or missing window seals and re-caulk frame as needed.
  • Repair or replace doors and hardware as needed for ADA accessibility and refresh finish surfaces.
  • Replace weatherstripping and door sweeps on exterior doors as needed.
  • Trim all vegetation overhanging roof.
  • Install gutter, downspouts, and splash blocks.
  • Update to ADA compliant plumbing fixtures in kitchen area.

Additional Projects, if Funds Become Available

  • Deep clean, repair or replace aged and damaged flooring.
  • Install additional receptacles in classroom.
  • Install LED lighting.
  • Install lighting control system.
  • Update restroom accessories and stalls for ADA compliance as needed.
  • Repair or replace aged or damaged cabinets and countertops as needed.
  • Replace damaged moveable furnishings as needed.
  • Refresh high touched interior wall finished surfaces.
  • Refresh painted ceiling finished surfaces.
  • See Safety & Security recommendations on the Facility Details page.
Educational Adequacy Assessment
System Rating Score
  • Adequate Spaces

  • Needs Improvement

  • Not Adequate

Fair
Core Classrooms: Classroom areas are generally in fair condition.
Visual and Performing Arts:
Cafeteria:
Fair
Occupant Flow: ADA assessable runs through DAEP classroom area.
Poor
Security: See Safety & Security recommendations on the Facility Details page.
Site Playgrounds/Extra Curricular:
Special Education:
Physical Education:
Library:
Administration:

Actions to Improve the Educational Environment

The educational environment of the facility is in fair condition. Security enhancements to facility should be made. Maintenance and repairs are needed to replace broken siding, refresh finished surfaces, and update technology systems.