Connally ISD - High School - Original 1950 Gym
- Year Built1950
- Square Footage11,050
- Replacement Cost$8,604,434
- Condition Budget$2,141,367
- Facility Condition Index30%
Condition Assessment
System Rating ScoreGood
Fair
(or will require attention in near future 3-10 years)
Poor
(or will require attention now 0-2 years)
Exterior
Good
Exterior Structure: Repair minor cracking on exterior masonry grout and brick.
Good
Foundation: No issues observed.
Good
Parking/Traffic: Counted with Football Athletics and Multipurpose.
Good
Site: No issues observed.
Fair
Doors: Refinish exterior doors and replace door hardware with ADA compliant hardware. Refinish interior doors and replace non-ADA compliant door hardware.
Good
Exterior/Interior Windows: No issues observed.
Good
Roof: Area 1: Roof overall is in good condition. Minor issues with ponding was observed. Roof fascia should be inspected and repaired and repainted as necessary. The roof should be inspected at least semi-annually and after every significant weather event.
Interior
Fair
Interior Structure: Refinish interior masonry walls. Remove and replace damaged wallboard walls. Replace stained, damaged, or sagging ceiling tiles.
Poor
Plumbing: Replace fixtures that are outdated, damaged, or do not comply with water efficiency standards. Building mechanical systems 30 years of age or older should be closely inspected and repaired or replaced as necessary.
Poor
ADA: Locker rooms need to be renovated to meet ADA compliance.
Poor
Furnishing, Fixtures, Equipment: Update restroom stalls and accessories to meet ADA compliance.
Fair
Electrical: Building mechanical systems 30 years of age or older should be closely inspected and repaired or replaced as necessary. Update lighting fixtures to LED fixtures.
Poor
Safety/Security: See Safety & Security recommendations on the Facility Details page.
Poor
Flooring: Replace damaged resilient floor tiles. Deep clean ceramic tile and grout, repair damaged tile and grout as necessary. Strip and re-apply liquid applied flooring.
Good
HVAC: No issues observed or reported.
Priority Projects
- See Safety & Security recommendations on the Facility Details page.
- Replace fixtures that are outdated, damaged, or do not comply with water efficiency standards.
- Building mechanical systems 30 years of age or older should be closely inspected and repaired or replaced as necessary.
- Repair and repaint damaged soffit and fascia.
- Refinish exterior doors and replace door hardware with ADA compliant hardware.
- Refinish interior doors and replace non-ADA compliant door hardware.
Additional Projects, if Funds Become Available
- Renovate locker rooms
- Replace bleachers
- Repair minor cracking on exterior masonry grout and brick.
- Refinish interior masonry walls.
- Remove and replace damaged wallboard walls.
- Replace stained, damaged, or sagging ceiling tiles.
- Update lighting fixtures to LED fixtures.
- Replace damaged resilient floor tiles.
- Deep clean ceramic tile and grout, repair damaged tile and grout as necessary.
- Strip and re-apply liquid applied flooring.
Educational Adequacy Assessment
System Rating ScoreAdequate Spaces
Needs Improvement
Not Adequate
Good
Occupant Flow: Occupant flow within the facility appears adequate.
Poor
Security: See Safety & Security recommendations on the Facility Details page.
Fair
Physical Education: Gym space is adequate as a practice gym. ADA compliant restrooms and locker rooms are needed.
Actions to Improve the Educational Environment
The educational environment of the facility is in fair condition. Accessible restrooms and locker rooms should be provided.