Priority Projects

AS High School - Ag Farm

  • Provide Safety & Security Improvements.
  • Test and remediate for mold.
  • Repair roof leak that caused major damage in concession area.
  • Replace damaged ceiling in concessions area.

AS High School - CTE/Weight Room

  • Provide adequate flammable storage.
  • Provide safety and security improvements.
  • 2 units are 13 years old and have two years expected life remaining; upgrade controls and provide testing and balancing when replacing HVAC units.
  • Accessible egress from all doors.

AS High School - Main

  • Provide recommended Safety & Security improvements.
  • Repair retaining wall and terracing at Aux.
  • HVAC replacement, controls upgrades and testing and balancing.
  • Repair and regrade catch basins at Aux Field.
  • Staff reported two leaks in need of location and immediate repair.
  • Replace ADA Parking signage at Ag Barn.
  • Provide adequately equipped Life Skills suite.
  • Relocate dumpster to at least 75' from the building Repair steps at sports venues.

AS High School - Field House/Athletics

  • Provide Safety & Security improvements.
  • Reseal SB & BB press box doors to prevent further interior water damage and replace rotten flooring in SB and BB press boxes.
  • Replace damaged backstop pads at SB.
  • Correct drainage on SB field.
  • Address moisture issues at dugouts.
  • Eliminate water intrusion through underground conduits at the FH.
  • Repair track and install structural topcoat at HS.

Transportation

  • Identify source of interior water damage and repair.
  • Replace damaged ceiling tiles.
  • Provide Safety & Security improvements found on the Facility Details page.
  • Provide exhaust control system.
  • Provide building signage.

Old School Site - Gymnasium (Main)

  • Sample for ACM, lead and abate as needed.
  • Secure a structural evaluation of foundation to determine measures needed; correct issues identified by engineering evaluation and provide adequate airways and crawlspace access.
  • Repair leaks evidenced by interior water damage.
  • Replace sidewalks.
  • Regrade to remove soil from contact with exterior walls and to provide positive drainage away from the building.
  • Trim trees and shrubbery back from building and roof line.
  • Provide Safety & Security improvements.
  • Provide accessible routes at all entrances.
  • Install proper pipe supports under building.
  • Provide accessible seating in gym.
  • Renovate restrooms to provide accessibility.
  • Provide accessible signage.
  • Conduct IAQ testing, remediate as needed, identify source of moisture and repair.

Old School Site - Old Maintenance

  • Replace rusting roof.
  • Provide accessibility upgrades to entrances, exterior and restroom.
  • Provide Safety & Security recommendations listed on the Facility Details page.
  • Replace windows.

Maintenance - Old Gym

  • Repair erosion at foundation.
  • Trim trees and shrubbery away from building.
  • See Safety & Security recommendations on the Facility Details page.
  • Clear debris from ramp and maintain for accessibility.
  • Evidence of pest/varmint intrusion, eliminate access points.
  • Provide Lighting Control System.

Maintenance - Main

  • Provide Safety & Security recommendations listed the Facility Details page.
  • Provide conditioning for spaces storing district records and furnishings.
  • Conduct IAQ testing, take humidity control steps and mediate as needed.
  • Provide adequate flammable storage.
  • Renovate RR's to provide accessible RR's.
  • Regrade to provide positive drainage away from building and to repair erosion.
  • Provide adequate, accessible signage.
  • Replace obsolete door hardware

AS Elementary

  • Provide Safety and Security Improvements.
  • Provide accessible site and exterior signage.
  • Complete repair or replacement of water heater.
  • Re-establish condensate drain lines (250').
  • Repair leaks at cooling tower.
  • Replace main section of modified bitumen roofing.
  • Replace soffit panels.
  • Repair and reseal roof flashing at masonry.
  • Perform maintenance of seams, fasteners, edges and flashings on metal roof system.
  • Restripe parking and fire lanes.
  • Repair/replace kitchen equipment.
  • Repair/replace walk-in freezer/cooler.
  • Repair erosion and install drainage structure on east side of building by Admin Pkg Lot.
  • Evaluate existing transformers for repaint, repair, or replacement.
  • Renovate playgrounds including 1) Refresh playground fall zone materials, 2) provide adequate fall zones at all playground equipment, 3) Provide accessible entry to playground sets, 4) Provide rubber base mats a base of slides and swings.
  • Provide ADA Improvements including: 1) Provide accessible ramp at SW exit, 2) provide accessible route to west playground, 3) provide concrete ramping at dumpsters, 4) Provide accessible entry to playground sets, 5) Provide adequate signage at HC seating in gym.
  • Provide appropriate restroom, changing and home skills spaces for Life Skills room.

Additional Projects, if Funds Become Available

AS High School - Ag Farm

  • Provide accessible signage.
  • Paint exposed structure in pen/arena area.
  • Clean exterior walls and treat with algaecide.
  • Paint exterior metal surfaces as needed.
  • Seal around AC unit.
  • Replace paving, interior wall sealants.
  • Paint walls as needed.
  • Paint interior structure.
  • Replace rusting light fixtures and corroded fans.

AS High School - CTE/Weight Room

  • Provide adequate flammable storage.
  • Provide piping to connect downspouts to storm sewer.
  • Provide canopies at all doors.
  • Accessible egress from all doors.
  • Provide additional storage in order to remove stored materials to allow 3' access area around electrical panels and equipment. Provide dedicated network closet.
  • Provide a weight room in close proximity to the Field House.
  • Convert existing weight room space into additional CTE spaces.
  • Clean exterior walls and treat with algaecide.
  • Paint exterior metal surfaces.
  • Repaint interior walls.
  • Replace damaged 2x2 ceiling tiles.
  • Clean high ceilings & Repaint high ceiling in CTE area.
  • Clean or replace HVAC grilles.
  • Identify causes of interior water damage and repair roof.
  • Paint exterior HM and all interior doors.
  • Repaint RR floors in CTE area.
  • Provide piping to connect downspouts to storm sewer.
  • Provide canopies at all doors.
  • Provide additional storage in order to remove stored materials to allow 3' access area around electrical panels and equipment.
  • Provide dedicated network closet.
  • Provide a weight room in close proximity to the Field House.
  • Convert existing weight room space into additional CTE spaces.

AS High School - Main

  • Provide Library addition, 987 sf.
  • Provide Kitchen addition, 1019 sf.
  • Provide Cafeteria addition, 1650 sf.
  • Expand electronic access control.
  • Provide 2nd Gymnasium to service JHS and HS PE and Athletics programs.
  • Provide adequately equipped Life Skills suite.
  • Provide additional Workroom - 284 sf.
  • Provide pole mounted site lighting at Ag Barn.
  • Relocate dumpster to at least 75' from the building.
  • Replace campus directional signage.
  • Replace all building and paving sealants, provide additional sealants b/t exterior walls and plaster soffits.
  • Clean exterior and treat with algaecide.
  • Minor repairs in stucco and metal trim.
  • Minor interior wall and ceiling repairs.
  • Provide transition boots at downspout-storm sewer joints.
  • Paint gas line at Main.
  • Replace exterior latches and add vandal proof covers.
  • Provide paved drive to FH and all stadiums.
  • Pave road to and parking lot at Ag Barn.
  • Restripe all parking and drives.
  • Correct condensation issues on walking freezer/cooler.
  • Repair PLAM casework and counter tops as needed.
  • Reconfigure fencing and gates around FH.
  • Repaint ornamental fencing at dining patio.
  • Correct drainage issues on N side of Ag Barn, downspouts at CTE building, drainage at swale between softball and football stadiums.
  • Regrade and pave south entry to provide accessible entry at Aux.
  • Trim or remove shrubbery away from Main building.
  • Repaint exterior doors, frames and mullions.
  • Repaint exterior HM windows.
  • Steam clean and seal kitchen tile floor.
  • Provide Library addition, 987 sf.
  • Provide Kitchen addition, 1019 sf.
  • Provide Cafeteria addition, 1650 sf.
  • Provide 2nd Gymnasium to serve JHS and HS PE and Athletics programs.
  • Provide additional Workroom - 284 sf.
  • Replace campus directional signage.
  • Provide additional storage to allow for proper clearance in mechanical and electrical rooms.
  • Additional locker rooms.
  • Additional CTE/Ag Facilities (storage, classroom, shop).
  • Auditorium, campus lacks full fly auditorium to support Fine Arts Programs.
  • Additional classrooms (ea).

AS High School - Field House/Athletics

  • Repair and resurface track including curb replacement foundation repair, rubber surface and structural topcoat at Aux Field.
  • Repair track and install structural topcoat at HS.
  • Remove old baseball infrastructure at ES (Aux Field).
  • Remove old tennis infrastructure at ES Playground (Aux Field).
  • Provide cover and lighting at SB and BB batting cages.
  • Consider adding partitions in the FB press box.
  • Replace sports field lighting at Aux Field.
  • Provide adequate dehumidification in the FH.
  • Provide adequate CCTV coverage for Field House and stadiums.
  • Provide weight room adjacent to Field House.
  • Provide practice fields adjacent to Field House.
  • Clean, seal and repaint dugout walls.
  • Repaint interior walls as needed (25%).
  • Repaint wallboard ceilings as needed (50%).
  • Provide cover and lighting at SB and BB batting cages.
  • Consider adding partitions in the FB press box.
  • Provide adequate dehumidification in the FH.
  • Remove old baseball infrastructure at ES (Aux Field).
  • Remove old tennis infrastructure at ES Playground (Aux Field).
  • Repair and resurface track including curb replacement foundation repair, rubber surface and structural topcoat at Aux Field.
  • Replace sports field lighting at Aux Field.
  • Provide weight room adjacent to Field House.
  • Provide practice fields adjacent to Field House.

Transportation

  • Provide canopy at fuel system.
  • Provide CCTV coverage.
  • Provide building signage.
  • Provide additional 8 spaces to bus parking.
  • Provide exhaust control system.
  • Provide bus wash with canopy.
  • Expand electronic access control.
  • Provide additional 8 spaces to bus parking.
  • Provide bus wash with canopy.
  • Provide canopy at fuel system.

Old School Site - Gymnasium (Main)

  • Provide Voice / Data System.
  • Provide Closed Circuit Surveillance.
  • Provide Access Control System.
  • Provide Intrusion Alarm System
  • Provide Fire Alarm / Detection.
  • Provide Lighting Control System.
  • Expand parking to accommodate seating capacity of 260 with 30 additional spaces to bring total to 65.
  • Provide gutters and downspouts.
  • Provide HVAC system for building.
  • Provide accessible routes at all entrances.
  • Install proper pipe supports under building.
  • Provide accessible seating in gym.
  • Renovate restrooms to provide accessibility.
  • Provide accessible signage.
  • Provide additional site lighting.
  • Remove fencing and structures from old softball field an old bus yard.
  • Conduct IAQ testing, remediate as needed, identify source of moisture and repair.
  • Renovate corridors to allow adequate space for circulation.
  • Repair damaged wood planking and plaster walls.
  • Paint interior walls.
  • Replace damaged wood plank ceilings and paint painted ceilings.
  • Replace 1x1 glue up tiles with 2x2 system.
  • Replace damaged siding after foundation corrections.
  • Replace damaged, old and obsolete fixtures to provide accessible restrooms.
  • Replace mechanical infrastructure older than 30 years.
  • Replace ductwork and HVAC grilles, ventilation fans and louvers.
  • Provide centralized HVAC system.
  • Maintain fasteners, sealants; repair soffit and fascia.
  • Replace roadway and parking paving and restripe.
  • Provide accessible seating.
  • Replace OH electrical service.
  • Replace wooden exterior and interior doors, frames and door hardware.
  • Replace original window units.
  • Replace vinyl floor coverings.
  • Repaint concrete floors.
  • Provide Voice / Data System.
  • Provide Lighting Control System.
  • Expand parking to accommodate seating capacity of 260 with 30 additional spaces to bring total to 65.
  • Provide gutters and downspouts.
  • Provide HVAC system for building.
  • Remove fencing and structures from old softball field an old bus yard.
  • Renovate corridors to allow adequate space for circulation.

Old School Site - Old Maintenance

  • Remove abandoned containment basins, slabs, mechanical pens.
  • Due to age, remote location, expense of repairs and improvements disposal is recommended.
  • Provide Voice / Data System.
  • Provide Clock / Intercom System.
  • Provide Access Control System.
  • Provide CCTV coverage.
  • Provide Intrusion alarm.
  • Provide Fire Detection / Alarm.
  • Provide Lighting control system.
  • Replace damaged wall panels and repaint exterior.
  • Paint interior walls.
  • Paint exposed structure.
  • Consider replacing all mechanical systems.
  • Replace OH service with underground.
  • Replace exterior doors, frames and hardware.
  • Repair, reseal, paint OH door.
  • Replace interior door, frame and hardware.
  • Remove abandoned containment basins, slabs, mechanical pens.
  • Provide Voice / Data System.
  • Provide Lighting control system.

Maintenance - Old Gym

  • Provide canopies at all entrances.
  • Clear debris from ramp and maintain for accessibility.
  • Provide additional site lighting.
  • Provide interior and exterior CCTV coverage.
  • Evidence of pest/varmint intrusion, eliminate access points.
  • Install additional interior metal wall panels.
  • Provide Voice / Data System.
  • Provide Clock / Intercom System.
  • Provide Access Control System.
  • Provide Intrusion Alarm System.
  • Provide Lighting Control System.
  • Provide HVAC for building.
  • Repair wall panels that are rusted at foundation.
  • Clean, replace damaged metal panels, repair wall insulation jacketing, repaint wall structural components.
  • Repaint open deck and exposed structure.
  • Repair insulation jacketing.
  • Maintain seals, flashings and fasteners; interior evidence points to minor leaks; locate and repair as needed.
  • Relace rusting conduit straps.
  • Paint and reseal exterior doors.
  • Provide canopies at all entrances.
  • Install additional interior metal wall panels.
  • Provide HVAC for building.

Maintenance - Main

  • Remove abandoned restrooms.
  • Provide conditioning for spaces storing district records and furnishings.
  • Provide awnings at each entry.
  • Provide adequate CCTV coverage.
  • Renovate Maintenance building to more efficiently utilize the available space.
  • Conduct IAQ testing, take humidity control steps and mediate as needed.
  • Provide adequate ventilation in shop.
  • Provide adequate flammable storage.
  • Provide electronic access control.
  • Provide adequate, accessible signage.
  • Sample and abate ACM as needed.
  • Replace flooring in maintenance office, hallway and furniture storage areas.
  • Replace single pane, aluminum windows.
  • Paint doors.
  • Replace wooden doorframes, threshold at S door of Maintenance building to prevent further interior water damage, interior doors and hardware.
  • Replace OH service with underground.
  • Replace electrical switchgear.
  • Replace inefficient lighting with LED.
  • Trim trees and shrubs away from buildings and rooflines.
  • Replace inefficient light fixtures with LED.
  • Replace furnishings and provide additional appropriate shelving.
  • Planning should begin for replacement of Maintenance and Athletic Storage buildings.
  • Identify sources of interior water damage and repair.
  • Evaluate mechanical systems older than 30 years for replacement.
  • Paint interior walls.
  • Repair and paint wallboard ceilings.
  • Replace 4x2 acoustic ceiling system with 2x2.
  • Clean and paint open deck areas.
  • Paint canopy.
  • Paint exterior wall panels.
  • Replace damaged metal wall panels.
  • Provide adequate ventilation in shop.
  • Renovate Maintenance building to more efficiently utilize the available space.
  • Provide awnings at each entry.
  • Remove abandoned restrooms.
  • Replace HVAC grilles.

AS Elementary

  • Kitchen addition of 953 sf.
  • Library addition of 568 sf.
  • Provide lighting controls.
  • Provide accessible site and exterior signage.
  • Pave parking area adjacent to old baseball field.
  • Expand perimeter fencing.
  • Remove baseball structures(lights, dugouts, bleachers, batting cages).
  • Provide additional canopy at front (350 sf) and all exits (8x125 sf = 1000 sf).
  • Replace and expand canopy at bus loading to cover students as they load onto buses (3750 sf).
  • Renovate playgrounds including 1) Refresh playground fall zone materials, 2) provide adequate fall zones at all playground equipment, 3) Provide accessible entry to playground sets, 4) Provide rubber base mats a base of slides and swings.
  • Provide ADA Improvements including: 1) Provide accessible ramp at SW exit, 2) provide accessible route to west playground, 3) provide concrete ramping at dumpsters, 4) Provide accessible entry to playground sets, 5) Provide adequate signage at HC seating in gym.
  • Provide storm water piping for downspouts in NE and SE courtyards.
  • Provide adequate custodial storage to facilitate evacuation of miscellaneous items from mechanical rooms.
  • Provide appropriate restroom, changing and home skills spaces for Life Skills room.
  • Provide a secure entry vestibule.
  • Provide additional outlets in Kitchen.
  • Provide administrative space off campus and convert vacated space to classrooms.
  • Expand fire sprinkler system to entire facility.
  • Replace sealants at sidewalks.
  • Replace sealants at doors, windows and expansion joints.
  • Clean exterior walls and treat with an algaecide.
  • Minor masonry and tuck-point repairs.
  • Replace damaged vents, equipment covers and lights.
  • Repaint exterior metal surfaces as needed.
  • Repair fencing at old baseball field; remove debris from base of fences.
  • Regrade at curbs, sidewalks and splash blocks.
  • Repaint HM doors.
  • Repair or replace interior hardware as needed.
  • Repair rutting along east end of building.
  • Provide barriers to prevent parking on lawn at E end of building.
  • Trim trees away from building.
  • Repaint HM window frames.
  • Replace gaskets and seals on aluminum windows.
  • Replace gym window glass with opaque translucent material.
  • Repaint interior walls.
  • Minor repairs to interior sheetrock walls.
  • Install new gym ceiling.
  • Provide conduit for surface mounted wiring in gym.
  • Replace sealants at drive and parking paving.
  • Repaint/refinish gym bleachers.
  • Provide appropriate solid surface countertops in Science rooms.
  • Recoat epoxy flooring in restrooms in 2004 addition.
  • Kitchen addition of 953 sf.
  • Library addition of 568 sf.
  • Provide lighting controls.
  • Pave parking area adjacent to old baseball field.
  • Remove baseball structures (lights, dugouts, bleachers, batting cages).
  • Provide additional canopy at front (350 sf) and all exits (8x125 sf = 1000 sf).
  • Replace and expand canopy at bus loading to cover students as they load onto buses (3750 sf).
  • Provide storm water piping for downspouts in NE and SE courtyards.
  • Provide adequate custodial storage to facilitate evacuation of miscellaneous items from mechanical rooms.
  • Provide additional outlets in Kitchen.
  • Provide administrative space off campus and convert vacated space to classrooms.

Completed Projects

AS High School - Ag Farm

  • No Projects

AS High School - CTE/Weight Room

  • No Projects

AS High School - Main

  • No Projects

AS High School - Field House/Athletics

  • No Projects

Transportation

  • No Projects

Old School Site - Gymnasium (Main)

  • No Projects

Old School Site - Old Maintenance

  • No Projects

Maintenance - Old Gym

  • No Projects

Maintenance - Main

  • No Projects

AS Elementary

  • No Projects

Facility Dashboard, and its Facility Condition Assessment (“FCA”) assumes “like for like” system(s). It does not take into consideration design changes or code upgrades. The Facility Condition Index (FCI) is a standard facility metric that evaluates a facilities identified deficiencies against the replacement cost of the entire facility to arrive at a replacement cost ratio. Our cost estimates are in current day dollars and should be used for planning purposes only. We encourage and recommend review and updating of your construction scope and estimates prior to seeking funding.