Priority Projects
Gonzales Elementary
- Replace 1 aging HVAC split-system unit.
- Clean stains on exterior masonry and recaulk all expansion joints.
- Recaulk all window frame/wall joints.
- Replace gutters and reseal roof panel joints to eliminate roof leaks.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
- Paint stripes in front of electrical panels to ensure 3' minimum clearance is maintained.
Gonzales Primary Academy
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
- Repair roof to eliminate leak occurring in one area between room 139 & cafeteria.
- Paint stripes in front of electrical panels to ensure 3' minimum clearance is maintained.
North Avenue Intermediate - 100-200-500 Buildings
- Replace carpeting in 100 building and clean carpeting in 200 building.
- Rebalance HVAC system to reduce CO2 levels in buildings.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
North Avenue Intermediate - 400 Building
- Rebalance HVAC system to reduce CO2 levels in building.
- Security improvements needed to create a more secure campus environment.
North Avenue Intermediate - Band Hall Building
- Security improvements needed to create a more secure campus environment.
North Avenue Intermediate - Cafeteria & 300 Buildings
- Repair exterior masonry cracks on south side of 300 building.
- Replace 2 aging HVAC units.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
North Avenue Intermediate - Gym Building
- Security improvements needed to create a more secure campus environment.
Gonzales Jr High - 100 Building (Main)
- Commission and rebalance HVAC system to reduce CO2 levels in building.
- Replacement of standing seam metal roof is needed if rusting edges cannot be economically repaired.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
Gonzales Jr High - 300 Building
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on at building to increase access for students, staff, and visitors.
Gonzales Jr High - Band Hall
- Security improvements needed to create a more secure campus environment.
Gonzales High School - Athletic Fields
- No high priority projects identified.
Gonzales High School - Gym/Classroom Building
- Hire engineer to investigate and identify any potential foundation problems.
- Security improvements needed to create a more secure building environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
Gonzales High School - Main Building
- Replace aging HVAC split-system units (3 units) and commission and rebalance HVAC system and provide additional fresh-air makeup to reduce CO2 levels in building.
- Replace of built-up gravel roof.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
Gonzales High School - Vocational Building
- Replace of built-up gravel roof.
- Security improvements needed to create a more secure building environment.
- Provide ADA improvements within building to increase access for students, staff, and visitors.
Support Facilities - Old Administration Building
- Security and safety improvements needed to create a more secure building environment.
- Provide ADA improvements at building to increase access for staff and visitors.
Support Facilities - Technology Center
- Replace asphalt shingle roof.
- Security improvements needed to create a more secure building environment.
- Provide ADA improvements at building to increase access for staff and visitors.
Support Facilities - Maintenance & Transportation Complex
- Provide ADA improvements at building to increase access for staff and visitors.
Support Facilities - Old Water Co-Op Building
- No priority projects at this time.
Support Facilities - Apache Field
- Provide ADA improvements at complex to increase access for students, staff, and visitors.
- Hire an engineer to investigate the structural integrity of the bleacher structures and light poles.
Administration (East Avenue Primary- Added Buildings)
- Security improvements needed to create a more secure campus environment.
Administration (East Avenue Primary-Original Buildings (100, 300, 400, 500 Buildings))
- Repair brick cracks at 100 and 500 building.
- See Safety & Security recommendations on the Facility Details page.
- Provide ADA improvements on campus to increase access for students, staff, and visitors.
Gonzales Jr High - Science, Auditorium, and Old Gym Building
- Replace aging HVAC split-system unit (1 of 9 units) and commission and rebalance HVAC system to reduce CO2 levels in building.
- Recaulk older windows and repaint window panels.
- Security improvements needed to create a more secure campus environment.
- Provide ADA improvements at the building to increase access for students, staff, and visitors.
Gonzales Jr High - Math Addition and New Gym Addition
- Security improvements needed to create a more secure campus environment.
Additional Projects, if Funds Become Available
Gonzales Elementary
- Provide canopies at playgrounds, repair damaged and worn equipment, and repair fall surfaces.
- Repaint exterior metal doors.
- Clean carpeting throughout the building.
- Construct kitchen addition to better serve campus population when campus is at or near full functional capacity.
- Construct library addition to better serve campus population when campus is at or near full functional capacity.
Gonzales Primary Academy
- Construct library addition to better serve campus population when campus is at or near full functional capacity.
- Construct addition to provide additional storage space for campus staff.
North Avenue Intermediate - 100-200-500 Buildings
- Repair and repaint stucco finishes and clean masonry on 200 building; repair and repaint undersides and poles of campus canopies & walkway covers.
- Provide canopy at parent pick-up student loading area.
- Asphalt parking lots need repair and resealing.
- Replace fiber wall coverings in hallways of 100 building and repair vinyl baseboards in 200 building.
- Replace mirrors in 200 building student restrooms.
- Fill holes on playground surfaces.
- Replace electrical and lighting infrastructure older than 30 years in 200 building.
- Replace plumbing infrastructure older than 30 years in 200 building and add sinks to the art room.
- Construct library addition to better serve campus population when campus is at or near full functional capacity.
- Expand parking by 5 additional spaces to better serve campus population when campus is at or near full functional capacity.
North Avenue Intermediate - 400 Building
- Repaint exterior metal doors.
- Repair frayed fiber wall covering in hallway.
- Replace cracked and damaged VCT.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
North Avenue Intermediate - Band Hall Building
- Repaint wallboard walls.
North Avenue Intermediate - Cafeteria & 300 Buildings
- Repair and repaint stucco soffits.
- Repaint exterior metal doors and refinish oxidized window frames at 300 building.
- Repaint wallboard walls in 300 building and replace ceiling tiles in 300 building.
- Replace cracked and damaged VCT in 300 building.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
- Begin planning for replacement of built-up gravel roof on 300 building within the next 10 years.
North Avenue Intermediate - Gym Building
- Repaint exterior metal doors.
- Repaint wallboard walls.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
Gonzales Jr High - 100 Building (Main)
- Repair brick cracks around building perimeter and repair missing/damaged protective grout covering on foundation perimeter.
- Provide canopies at parent pick-up student loading areas.
- Asphalt parking lots need repair and resealing.
- Repair cracks and uneven joints on campus sidewalks.
- Repair cracks in interior CMU walls and repair and repaint wallboard and wood panel walls.
- Repaint concrete floors in student restrooms.
- Replace older plumbing fixtures and stalls in student restrooms.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
- Construct library addition to better serve campus population when campus is at or near full functional capacity.
- Construct campus addition to house Art, ISS, and training programs currently housed in 3 portable buildings.
- Expand parking by 53 additional spaces to better serve campus population when campus is at or near full functional capacity.
Gonzales Jr High - 300 Building
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
- Construct cafeteria kitchen addition to better serve campus population when campus is at or near full functional capacity.
Gonzales Jr High - Band Hall
- Clean out debris in gutters.
- Repaint exterior doors.
- Replace ceiling tiles.
Gonzales High School - Athletic Fields
- Repaint baseball backstops and light poles, and repair of baseball batting cages.
- Reseal tennis court surfaces.
- Provide synthetic turf surface at football practice field and replace lights and poles at football practice field.
Gonzales High School - Gym/Classroom Building
- Clean stains on exterior CMU walls and recaulk expansion joints; repaint metal structure at front entry porch.
- Reseal gutter joints.
- Repaint interior CMU and wallboard walls.
- Replace VCT flooring.
- Construct library addition to better serve campus population when campus is at or near full functional capacity.
Gonzales High School - Main Building
- Repaint tilt-up concrete walls.
- Replace glazing compound on old 1st floor windows and repaint adjacent trim.
- Provide canopies at bus pick-up student loading areas.
- Repair and reseal asphalt parking lots and drives.
- Repaint exterior metal doors and refinish interior wood doors.
- Repair cracks in interior masonry walls, and repair and repaint wallboard and masonry walls; repair ceramic tile damage in restrooms.
- Replace VCT flooring at 1st floor.
- Replace ceiling tiles in older areas and repaint gym ceiling.
- Repair steps on interior stairways.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
- Construct kitchen addition to better serve campus population when campus is at or near full functional capacity.
- Construct teacher workroom/lounge addition to provide adequate support space for teachers.
- Construct campus addition to house cosmetology and classroom programs currently housed in 2 portable buildings.
Gonzales High School - Vocational Building
- Repaint tilt-up concrete walls.
- Replace glazing compound all windows.
- Repaint exterior metal doors and refinish interior wood doors.
- Clean vinyl walls, and repair and repaint wallboard walls.
- Replace VCT flooring.
- Replace ceiling tiles and repaint exposed structure ceilings.
- Replace older plumbing fixtures and stalls in student restrooms.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
Support Facilities - Old Administration Building
- No other projects identified at this time.
Support Facilities - Technology Center
- Trim trees growing over roofline.
- Repaint interior wallboard walls and replace ceiling tiles.
- Replace carpeting throughout the building.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
Support Facilities - Maintenance & Transportation Complex
- Repaint interior wallboard walls and replace ceiling tiles.
- Replace carpeting in maintenance office and VCT in transportation barn breakroom.
- Replace plumbing fixtures in transportation shop restroom.
- Renovate portable buildings, or replace with permanent structure.
Support Facilities - Old Water Co-Op Building
- Substantial interior renovation and rebuild needed to bring interior space into useable condition; renovation needs to also address safety/security and ADA provisions.
- Repave asphalt parking area.
- Replace windows.
- Repaint exterior doors.
- Clean (power wash) exterior metal panels on main building.
- Repair damaged downspouts.
Support Facilities - Apache Field
- Repave gravel lots with asphalt paving.
- Replace grass field with artificial turf playing field.
- Repaint structural components of bleachers, exterior wood and metal walls at support facilities, and exterior metal doors.
- Repair and repaint interior walls of support facilities.
- Replace carpeting in the press box.
- Replace older plumbing fixtures and stalls in visitors locker rooms and restrooms.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
Administration (East Avenue Primary- Added Buildings)
- Clean metal siding on all buildings.
- Repair and repaint gym ceiling.
- Construct library addition to better serve campus population when campus is at or near full functional capacity.
Administration (East Avenue Primary-Original Buildings (100, 300, 400, 500 Buildings))
- Repair and repave all asphalt parking and drive surfaces.
- Repaint structural elements of campus canopies and walkway covers.
- Repair and repaint interior wood doors.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
Gonzales Jr High - Science, Auditorium, and Old Gym Building
- On older portion of the building, the following is needed: repainting of older exterior metal doors and older interior wood doors; repainting of masonry and stucco walls in science wing and old gym; repainting of wallboard ceilings; repainting of ceiling structure in old gym; and replacement of ceiling tiles in science wing.
- Replace electrical and lighting infrastructure older than 30 years.
- Replace plumbing infrastructure older than 30 years.
- Construct science room expansions to better serve campus population when campus is at or near full functional capacity.
Gonzales Jr High - Math Addition and New Gym Addition
- No additional projects identified.
Completed Projects
Gonzales Elementary
- No Projects
Gonzales Primary Academy
- No Projects
North Avenue Intermediate - 100-200-500 Buildings
- No Projects
North Avenue Intermediate - 400 Building
- No Projects
North Avenue Intermediate - Band Hall Building
- No Projects
North Avenue Intermediate - Cafeteria & 300 Buildings
- No Projects
North Avenue Intermediate - Gym Building
- No Projects
Gonzales Jr High - 100 Building (Main)
- No Projects
Gonzales Jr High - 300 Building
- No Projects
Gonzales Jr High - Band Hall
- No Projects
Gonzales High School - Athletic Fields
- No Projects
Gonzales High School - Gym/Classroom Building
- No Projects
Gonzales High School - Main Building
- No Projects
Gonzales High School - Vocational Building
- No Projects
Support Facilities - Old Administration Building
- No Projects
Support Facilities - Technology Center
- No Projects
Support Facilities - Maintenance & Transportation Complex
- No Projects
Support Facilities - Old Water Co-Op Building
- No Projects
Support Facilities - Apache Field
- No Projects
Administration (East Avenue Primary- Added Buildings)
- No Projects
Administration (East Avenue Primary-Original Buildings (100, 300, 400, 500 Buildings))
- No Projects
Gonzales Jr High - Science, Auditorium, and Old Gym Building
- No Projects
Gonzales Jr High - Math Addition and New Gym Addition
- No Projects
Facility Dashboard, and its Facility Condition Assessment (“FCA”) assumes “like for like” system(s). It does not take into consideration design changes or code upgrades. The Facility Condition Index (FCI) is a standard facility metric that evaluates a facilities identified deficiencies against the replacement cost of the entire facility to arrive at a replacement cost ratio. Our cost estimates are in current day dollars and should be used for planning purposes only. We encourage and recommend review and updating of your construction scope and estimates prior to seeking funding.