Early Childhood
color for 0-40% 0-40%
color for 41-70% 41-70%
color for 71-100% 71-100% FCI
Facility Scorecard
Name: Early Childhood
Address: 100 B.B. Brown Dr Waco, TX 76705
Year Built: 1989
Square Footage: 46,445
Replacement Cost Built: $26,119,799
Condition Budget: $6,187,924
Facility Condition Index: 29%
Executive Summary

Built in 1989, the Connally Early Childhood School facility is in good condition but is in need of maintenance and repair of various building components. The roof systems should be replaced due to age and substantial evidence of roof leaks. The interior finishes should be refreshed. Energy efficiency updates to double pane windows and LED lighting is recommended. In addition, safety and security enhancements should be considered. In all, the interior of the facility is in good condition and provides a well-maintained educational environment that is conducive to learning. With adequate maintenance, the campus should continue to serve the district for an additional 25-30 years.